Timelines
| Phase | Detail | Target Timing |
|---|---|---|
| Launch | Announce the program; call for applications | September 2020 |
| Applications | Applications downloaded via REConstruct website and submitted via email Preliminary review for eligibility | September to end 2020 |
| Assessments | Local installers undertake preliminary assessments of applications | Within 6 weeks of application receipt |
| Approval | Formal project approvals, based on installer recommendation Panels and inverter allocated to installer | Within 2 weeks of recommendation |
| Installation | To be scheduled by installer in consultation with recipient | Within 2 months of project approval (assumes infrastructure is built) |